132kV Tyco XLPE New Install

Location: Clancy Docwra / UKPN

This project is a part overlay of an existing 132kV Fluid Filled Circuit. This comprised of five joint bays of Tyco Three Piece Shield Break Joints, one set of Tyco Outdoor Terminations, one joint bay of NKT Transitions Joints, Link Boxes and Pilot cable joints. We also had to decommission part of the existing circuit, cutting & capping the cable and extracting the cable fluid.
Project Images (Click to enlarge)